U.S. Infrastructure · Data Centers & Power

The bottleneck isn't land.
It's power.

AI data centers are scaling faster than the grid can deliver electricity. Here's where the constraint actually bites.

4,767
facility sites mapped
2,290GW
stuck in interconnection queues
55mo
median wait to connect new power

Data centers get built in ~2 years. New power generation now waits 4.5+ years to connect. That gap is the story.

Sources: LBNL Queued Up 2025 · EIA · CBRE H2 2025 · ISO/RTO operators
--:--:--
---
Layers
Results
Advanced Filters
Growth Status
All
New Since 2022
Expanded
Nuclear Proximity
All
0-50 mi
50-100 mi
100+ mi
Tools
Sources
2022 baseline: user-curated KML from datacenters.com
2026 current: OpenStreetMap Overpass API (ODbL)
Capacity: CBRE H2 2025 / JLL Year-End 2025
Reactors: NRC operating list
Grid capacity & peak: EIA-860 / ISO-RTO operators
Interconnection queues: LBNL Queued Up 2025
ISO boundaries: HIFLD (FERC/ORNL)
Tiles: CARTO Dark Matter / OpenStreetMap
--° N, --° E
Zoom -- · Click clusters to zoom · Click points for details